230 Acre Distribution Facility
Sealy, Texas
Completed all the Heavy / Civil Site Work including:
- Earthwork
- Site utilities and storm water system
- Soil stabilization
- Concrete paving
- Base installation - 150,000 tons
- Asphalt paving - 96,000 tons
900,000 CY of earth material moved - 35,000 CY per day!