Brazos Yard Departure And Yard Tracks
Completed Over 54,000 Tf Of New Track And 3 Turnouts
54k Tf
54,000 Tf Of New Track And 3 Turnouts

Brazos Yard Departure And Yard Tracks
Completed Over 54,000 Tf Of New Track And 3 Turnouts
Date Time Action
11/12/21 12:30 pm Pre-bid call.
11/12/21 3:30 pm Job proposal due.
11/12/21 6:30 pm Notice of award via phone.
11/15/21 7:00 am Mobilization of equipment.
11/16/21 7:00 am Boots on the ground.
12/22/21 5:30 pm 3 Departure tracks ready for service.
01/05/22 5:30 pm Finished ~23K feet of storage track.
9,016 Work Hours With Zero Recordables!