Tenaris Pipe Mill - Bay City
Tenaris Pipe Mill
150k man hours
150,000 man-hours without lost time
95
95 personnel including sub-contractors
60
60 pieces of earth-moving equipment

Tenaris Pipe Mill
Bay City, Texas
- Site clearing and grubbing
- Constructed 1.3 MM SF pipe-mill structural building pad 3-weeks ahead of schedule not including 15 rain days
- Excavated and embanked over 1.5 MM CY of earth material
- Installed complete storm water system including over 10,000 LF of UG pipe
- Soil stabilized over 48 acres utilizing 2,400 tons of lime
- Installed over 250,000 SY of geo-grid material
- Imported and placed to line and grade 400,000 tons of aggregate base
Forces peaked at 95 personnel including sub-contractors. Utilized over 60 pieces of earth-moving equipment. Site management included 1 project manager, 1 project engineer, 1 survey crew, 1 site safety officer and 2 site superintendents.
150,000 man-hours without lost time








Contact the Experts in Heavy Civil & Turnkey Railroad Construction
Today
Looking for expert site preparation and railroad construction? Partner with W.T. Byler Co. for safe, efficient, and exceptional project delivery. Delivering industry leading solutions since 1973.
Custom Construction & Railroad Solutions
View all services